0424 916 895 admin@goengineering.net.au LinkedIn

Insights

Five ways to manage uncertainty and keep a mine plan inside its budget

10/09/2026

By Jose Grado, Senior Mining Consultant Uncertainty is part of mining. Ground conditions change, equipment goes down, weather intervenes, priorities shift. None of that is unusual, and none of it is avoidable. What is avoidable is a plan that falls …

Five ways to manage uncertainty and keep a mine plan inside its budget

By Jose Grado, Senior Mining Consultant

Uncertainty is part of mining. Ground conditions change, equipment goes down, weather intervenes, priorities shift. None of that is unusual, and none of it is avoidable.

What is avoidable is a plan that falls apart the first time reality does something unexpected — and then takes the budget with it.

Over 13 years across underground and open-pit operations, and now working on the consulting side, I have seen the same handful of habits separate plans that hold from plans that don't. Here are the five I keep coming back to.

1. Build flexibility into the plan, and define where contingency sits

A plan that only works if everything goes right is not a plan. It is a forecast.

Building flexibility means designing the schedule so that it can absorb a disruption without a full re-plan — alternative mining areas that can be brought forward, sequences that are not so tightly coupled that one delay cascades through everything downstream, equipment assumptions that are not sitting at theoretical maximum utilisation.

Equally important is being explicit about where the contingency is. Contingency that is quietly buried inside individual task durations is contingency you cannot see, cannot manage and cannot report on — and it will get consumed early without anyone noticing. Define it, name it, put it where it belongs, and track what is drawn against it.

2. Identify the priority tasks and find the critical path

Not every task carries the same weight. Some can slip a week with no consequence at all. Others will move the completion date by exactly as much as they slip.

Identifying priority tasks and prioritising them accordingly is what gets you to the critical path — the sequence of work that genuinely determines the outcome. Once you know what sits on it, the conversation on site changes. Attention, equipment and people go where they will actually make a difference, instead of being spread evenly across work that does not need it.

It also changes how you respond to problems. A delay on the critical path is a schedule event that needs a decision today. A delay off it may simply need monitoring. Knowing which one you are looking at, in the moment, is worth a great deal.

3. Identify the risks — properly

The third habit is to work through what can harm the plan, deliberately and in advance. Geotechnical, equipment availability, dependence on a single contractor or a single piece of gear, access constraints, approvals, weather windows, grade variability against the resource model.

The value here is not the register. It is the thinking that produces it. A risk you have named in advance is one you can put a trigger and a response against. A risk you have not named becomes a crisis, and crises are expensive — not just in direct cost but in the disruption they cause to everything happening around them.

4. Align the technical requirements with the operational capability

This is the one I would emphasise most, because it is the most common failure I see.

A plan can be technically excellent and still be undeliverable. If the schedule assumes productivity rates the fleet has never achieved, or a level of drill and blast precision the crews are not currently set up to deliver, or a development rate that the ventilation and services cannot support — it will not matter how sound the design is. The plan will not survive contact with the site.

So the technical requirements have to be aligned with the operational capability of that specific operation. Not an industry benchmark. Not what a comparable mine achieves. Whatthisoperation, withthisfleet andthiscrew, can actually sustain.

That sometimes means having an uncomfortable conversation early. It is far cheaper than the alternative, which is discovering the gap three months into execution when the variance is already locked in.

5. Track, review and adapt

Finally, the plan is not finished when it is issued.

Track performance against it, review it on a regular cycle, and adapt it as things change on site or within the business. Changes are not a sign the plan was wrong. They are the normal condition of an operating mine. What matters is whether the plan is updated to reflect them, or quietly left to drift until the gap between plan and reality is too large to close.

A plan that is reviewed and adapted keeps its value as a decision-making tool. One that is not becomes a document people stop consulting — and at that point you have lost your control on the budget entirely.

None of these five are complicated. That is rather the point. Managing uncertainty is not about eliminating it — it is about building a plan that expects it, and then staying close enough to the plan to respond when it arrives.

Want to take the pressure off your next plan? Get in touch with the Go Engineering consulting team.

Client and site details are kept confidential. We describe the nature of the work — commodities, methods and outcomes — rather than naming engagements.